| BOP Stack |
|
|
| Has the Annular rubber been visually inspected at Rig-up? |
|
|
| Did you verify the RAM rubber configuration? |
|
|
| Has the BOP been Low- and High pressure tested? |
|
|
| No leakages from weep holes observed? |
|
|
| Are handwheels available (on location) to lock the rams? |
|
|
| Are the Shear rams capable of shearing the DP in use? |
|
|
| Is there a NRV installed in the Kill line? If not, do you have a dispensation? |
|
|
| Have the side outlets been fitted with WECO connections? |
|
|
| Are the handwheels on the side outlet v/v’s locked & installed? |
|
|
| Are all snublines installed on the HP lines? |
|
|
| Is there a pressure gauge installed on the 13-3/8″and 9-5/8″ Annulus? What do they read? |
|
|
| |
|
|
| REMOTE CHOKE PANEL |
|
|
| Are all gauges on the remote choke panel working? |
|
|
| Can the Poor Boy degasser & Choke Manifold Pressure gauges be read from this position? |
|
|
| Have all functions on the remote choke panel been tested? |
|
|
| Is the emergency back-up for choke control working? |
|
|
| Is the MAASP auto control by-passed on the choke panel? |
|
|
| |
|
|
| ECS Unit |
|
|
| Are gas sensors calibrated ? |
|
|
| |
|
|
| KOOMEY UNIT |
|
|
| Has an Accumulator test been done? What was the final pressure? |
|
|
| Are Closing & Open times the same as last time? |
|
|
| Are there any known defects on the Koomey unit? |
|
|
| Are the remote controls checked and function tested? |
|
|
| What is the minimum air pressure for the air pumps to operate the system? |
|
|
| |
|
|
| RIG-FLOOR |
|
|
| Is there a Kellycock Key available? |
|
|
| Is the Kellycock ready to be stabbed, using lifting handles? |
|
|
| Is a Gray v/v available, pressure-tested, thread clean? |
|
|
| X-over’s on the rigfloor for DC’s to Kellycock? |
|
|
| Are all gauges working and calibrated? |
|
|
| Is the Close-in procedure posted in the doghouse? |
|
|
| Is the Pre-kick sheet up-to-date? |
|
|
| Is the Flow-show working? |
|
|
| |
|
|
| MUD-GAS SEPARATOR |
|
|
| Mud gas separator (Poor Boy degasser) flushed, i.e. mudseal not plugged? |
|
|
| Is there a gauge installed on the Poor Boy degasser? |
|
|
| Are all connections tight on the Poor Boy degasser? |
|
|
| Flare line installed = 150 meter? |
|
|
| What is the maximum circulating rate for the PB degasser? |
|
|
| Has the MGS been tested and achieved a 5 Psi drawdown? |
|
|
| Has the Vacuum degasser been run and tested? How much dawdown was created? |
|
|
| Are V-belts onsite for the Vacuum degasser? |
|
|
| |
|
|
| TRIP & STRIP TANK |
|
|
| Has the stripping bottle precharge pressure been checked? |
|
|
| Is striptank pump working? |
|
|
| Is striptank cleaned and reading clearly visible? |
|
|
| Is triptank clean and system function tested? |
|
|
| |
|
|
| PLANNING |
|
|
| Will a Kick-drill be done before drilling out Shoetrack? |
|
|
| Will a Choke-drill be done before drilling out the Shoetrack? |
|
|
| Did STP and DSV check line-up? |
|
|
| Do you have a calibrated pressure gauge in your office? |
|
|
| Is there a ditch magnet available? |
|
|
| What is the maximum allowable Swab-Volume? |
|
|
| Have driller been instructed on depths of HC zones? |
|
|
| What is your minimum overbalance on HC zones? |
|
|
| Did you check the Drilling program for any hazards identified? |
|
|
| Clear instructions to ECS posted? |
|
|
| Do key personnel have their IWCF or equivalent WellCaP? |
|
|
| Is there at least 50 MT Barites on site? |
|
|
| Graph paper available from contractor STP to make Kill graph? |
|
|
| Are all recording devices in the EDC office working? |
|
|
| Are mixing hoppers in good condition? |
|
|
| Is there a CLEAR action plan in place, of who is doing what, in well control situations? |
|
|
| |
|
|